BREAKDOWN OF UNIT PRICE
Item: (C01D2) Concrete-3500psi-3rd Floor Roof
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-3500ps
100.000
cft
250.00
25000.00
Sub-Total(A1)
25000.00
8828.75
B4.Labour SuperStructu
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Structure at 3rd Floor
86.455
sft
125.35
10837.13
Sub-Total(B4)
10837.13
3827.13
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Concrete Pump above G.F.
400.000
cft
0.75
300.00
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
1400.00
494.41
Total(1)
13150.29
Add over head on Total(1)
5.0 %
657.51
Total(2)
13807.81
Add Profit on Total(2)
10.0 %
1380.78
Total(3)
15188.59
Add VAT on Unit Price
5.5 %
933.38
Add Income Tax on Unit Price
5.0 %
848.52
Unit Price
16970.49
Say
16970
per cum