BREAKDOWN OF UNIT PRICE
Item: (B05B) Lean Concrete-80 mm Thick
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ready Mix Concrete-2500ps
100.000
cft
200.00
20000.00
Sub-Total(A1)
20000.00
7063.00
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Concrete Pump upto Gr.flr
100.000
cft
8.00
800.00
Sub-Total(E1)
800.00
282.52
Total(1)
7345.52
Add over head on Total(1)
5.0 %
367.28
Total(2)
7712.80
Add Profit on Total(2)
10.0 %
771.28
Total(3)
8484.08
Add VAT on Unit Price
5.5 %
521.37
Add Income Tax on Unit Price
5.0 %
473.97
Unit Price
9479.41
Say
9479
per M3