BREAKDOWN OF UNIT PRICE
Item: (B03B) Earth Excavation from 5m to 10m
Basis:100 cft
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Excavation from 16-33ft
100.000
cft
20.00
2000.00
Sub-Total(B3)
2000.00
706.30
Total(1)
706.30
Add over head on Total(1)
5.0 %
35.32
Total(2)
741.62
Add Profit on Total(2)
10.0 %
74.16
Total(3)
815.78
Add VAT on Unit Price
5.5 %
50.13
Add Income Tax on Unit Price
5.0 %
45.57
Unit Price
911.48
Say
911
per M3