BREAKDOWN OF UNIT PRICE
Item: (B03A1) Earth Work in Excavation
Basis:1000 cft
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
10.000
no.
500.00
5000.00
Skilled Labour/ Helper
2.500
no.
550.00
1375.00
Mason1
0.250
no.
700.00
175.00
Sub-Total(B2)
6550.00
231.31
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
0.417
no.
700.00
291.90
Sub-Total(D1)
291.90
10.31
Total(1)
241.62
Add over head on Total(1)
5.0 %
12.08
Total(2)
253.70
Add Profit on Total(2)
10.0 %
25.37
Total(3)
279.07
Add VAT on Unit Price
5.5 %
17.15
Add Income Tax on Unit Price
5.0 %
15.59
Unit Price
311.81
Say
312
per Cum