BREAKDOWN OF UNIT PRICE
Item: (B02B7) Sand Filling (FM=0.5-0.8)
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Viti Sand (FM=0.5-0.8)
130.000
cft
15.00
1950.00
Sub-Total(A1)
1950.00
688.64
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.667
no.
500.00
333.50
Head Mason
0.125
no.
1000.00
125.00
Sub-Total(B2)
458.50
161.92
D1.Design/Prelims
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage (Labour)
0.100
no.
700.00
70.00
Sub-Total(D1)
70.00
24.72
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Compactor
100.000
cft
5.00
500.00
Sub-Total(E1)
500.00
176.58
Total(1)
1051.86
Add over head on Total(1)
5.0 %
52.59
Total(2)
1104.45
Add Profit on Total(2)
10.0 %
110.45
Total(3)
1214.90
Add VAT on Unit Price
5.5 %
74.66
Add Income Tax on Unit Price
5.0 %
67.87
Unit Price
1357.42
Say
1357
per Cum