BREAKDOWN OF UNIT PRICE
Item: (B01CG) Spacer CC for Pile Reinforcement
Basis:600 no.
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
12.000
bag
375.00
4500.00
Sylhet Sand (FM=2.2)
20.000
cft
54.00
1080.00
Sub-Total(A1)
5580.00
9.30
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile ReinCC Spacer Making
600.000
no.
10.00
6000.00
Sub-Total(B2)
6000.00
10.00
Total(1)
19.30
Add over head on Total(1)
5.0 %
0.97
Total(2)
20.27
Add Profit on Total(2)
10.0 %
2.03
Total(3)
22.29
Add VAT on Unit Price
5.5 %
1.37
Add Income Tax on Unit Price
5.0 %
1.25
Unit Price
24.91
Say
25
per no.