BREAKDOWN OF UNIT PRICE
Item: (B01CA) Re-bar Fabricating-Shore Pile
Basis:1000 kg.
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Fabriaction-Piling
1000.000
kg
15.00
15000.00
Sub-Total(B2)
15000.00
15000.00
B3.Labour-Substructur-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar Unloading
1000.000
kg
3.00
3000.00
Sub-Total(B3)
3000.00
3000.00
D2.Others-Structure
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire 24 BWG
8.000
kg
120.00
960.00
Sub-Total(D2)
960.00
960.00
Total(1)
18960.00
Add over head on Total(1)
5.0 %
948.00
Total(2)
19908.00
Add Profit on Total(2)
10.0 %
1990.80
Total(3)
21898.80
Add VAT on Unit Price
5.5 %
1345.74
Add Income Tax on Unit Price
5.0 %
1223.40
Unit Price
24467.93
Say
24468
per Ton