BREAKDOWN OF UNIT PRICE
Item: (B01C8) Spacer Insatallation-Shore Pile
Basis:1 no.
B2.Labour-Substructur-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Spacer for Pile Rod
1.000
no.
15.00
15.00
Sub-Total(B2)
15.00
15.00
Total(1)
15.00
Add over head on Total(1)
5.0 %
0.75
Total(2)
15.75
Add Profit on Total(2)
10.0 %
1.58
Total(3)
17.33
Add VAT on Unit Price
5.5 %
1.06
Add Income Tax on Unit Price
5.0 %
0.97
Unit Price
19.36
Say
19
per No.