BREAKDOWN OF UNIT PRICE
Item: (B01BD) RCC(1:1.25:2.5)-Super-structure
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement-CEM-II/A,52.5-PCC
25.250
bag
375.00
9468.75
Sylhet Sand (FM=2.2)
40.000
cft
54.00
2160.00
Stone-chips-20mm
80.000
cft
195.00
15600.00
Sub-Total(A1)
27228.75
9615.83
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Vibrator and Mixer M/c
100.000
cft
3.00
300.00
Sub-Total(E1)
300.00
105.95
Total(1)
9721.78
Add over head on Total(1)
5.0 %
486.09
Total(2)
10207.87
Add Profit on Total(2)
10.0 %
1020.79
Total(3)
11228.65
Add VAT on Unit Price
5.5 %
690.03
Add Income Tax on Unit Price
5.0 %
627.30
Unit Price
12545.98
Say
12546
per Cum