BREAKDOWN OF UNIT PRICE
Item: (A03F) Site Development-Filling Sand
Basis:100 cft
A1.Material Cost-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Viti Sand (FM=0.5-0.8)
130.000
cft
15.00
1950.00
Sub-Total(A1)
1950.00
688.64
B1.Labour-Prelimnaries
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.250
nos.
800.00
200.00
Labour
1.000
nos.
600.00
600.00
Sub-Total(B1)
800.00
282.52
E1.Equipment Cost
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Compactor
100.000
cft
5.00
500.00
Sub-Total(E1)
500.00
176.58
Total(1)
1147.74
Add over head on Total(1)
5.0 %
57.39
Total(2)
1205.12
Add Profit on Total(2)
10.0 %
120.51
Total(3)
1325.64
Add VAT on Unit Price
5.5 %
81.46
Add Income Tax on Unit Price
5.0 %
74.06
Unit Price
1481.16
Say
1481
per cum